The Lodges

Description
Lodges – Site is to subgrade. Phase 1 base asphalt is paved. Phase 2 and 3 have stone base placed and ready to pave. All storm utilities are installed. All sanitary sewer and services are installed. Water main is installed, fixing to start installing the services to each building.