Exeter River Ridge

Description
The project is currently 60% complete. Phase 1 is close to complete with only surface and concrete curbing to complete and minimal Earth moving and completing headwall installation. Phase 2 the majority of Earth moving remains and completing the purposed building and pavement areas.